News

Largest Order-Back Log in Clean Marine Switchboards History!

Clean Marine Switchboards (CMSw) are pleased to announce the largest order backlog in the history of the company. After a challenging period in 2018 and early 2019, the company has now stabilized its production capacity and implementations for even bigger growth in the time to come. The order backlog alone for 2020 already exceeds well above 35 MNOK and includes the following vessels:

  • 1 x DREDGING VESSEL – Built in BRAZIL. This is CMSw’s first large international contract with the complete system integration. The contract is signed directly between the design company/yard and CMSw. The scope of supply includes:
    • 2 x Main 400V Switchboards
    • 2 x Main 230V Switchboards
    • 1 x Emergency 400V/230V Switchboard
    • Power Management System (PMS)
    • Integrated Alarm System (IAS)
    • Navigation Lights Package
    • Internal Lighting Package
    • External Lighting Package
    • PA & GA System
    • Cables, Switches, Sockets
    • Electrical Engineering of the complete Scope
    • Commissioning
  • 4 x Wellboats + 1 Option vessel – Built in Norway. The scope of supply includes:
    • 5 x Main 440V Switchboards
    • 5 x Main 230V Switchboards
    • 5 x Emergency 440V/230V Switchboard
    • 2 x Power Management Systems (PMS)
    • Electrical Engineering of the mentioned scope
    • Commissioning
  • 3 x Wind Supply vessels – Built in Norway – The scope of supply includes:
    • 3 x Main 690V Switchboards
    • 3 x Main 440V Switchboards
    • 3 x Main 230V Switchboards
    • 3 x Emergency 440V/230V Switchboard
    • Electrical Engineering of the mentioned scope
    • Commissioning
  • 1 x Catamaran Tourist Vessel to operate in the Norwegian Fjords – Built in Norway – The scope of supply includes:
    • 1 x Main 400V Switchboard
    • 1 x Main 700VDC Multi-Drive Switchboard
    • CMSw’s Touchscreen solutions
  • Commissioning for the following projects delivered from CMSw in 2019:
    • 3 x Wellboats (2x in Norway, 1 x in Spain)
    • 1 x Wind Supply Vessel (Norway)
    • 1 x Retrofit Wind Supply Vessel (Belgium)
    • 1 x Fishing Vessel (Norway)

Further on CMSw have many projects on the “Hot List” which we hope to sign contracts for shortly. This includes both national and international projects.